If m men can do a work in r days, then the number of days taken by (m + n) men to do it is : |
| A. | (m +n)/mn |
| B. | (m +n)/mr |
| C. | mr/(m +n) |
| D. | r(m +n)/mn |
| Answer» D. r(m +n)/mn | |