If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good |
A. | EF = ES + D |
B. | LS = LFD |
C. | LF = LS + D |
D. | All of the above |
Answer» E. | |