1.

If duration of activity f is changed to 10 days, then the critical path for the project is

A. Critical path remains the same and the total duration to complete the project changes to 19 days.
B. Critical path and the total duration to complete the project remains the same.
C. Critical path changes but the total duration tocomplete the project remains the same.
D. Critical path changes and the total duration to complete the project changes to 17 days.
Answer» B. Critical path and the total duration to complete the project remains the same.