| 1. |
If D = duration, EF = earliest finish time, ES = earliest start time, LF = latest finish time, LS = latest start time, which relationship does not hold? |
| A. | EF = D - ES |
| B. | EF = D + ES |
| C. | LF = LS + D |
| D. | None of the above |
| E. | Supply and demand conditions |
| Answer» B. EF = D + ES | |