If A can complete a work in 36 days and B can do the same work in 42days. If A after doing 6 days, leaves the work, find in how many days B will do the remaining work ? |
A. | 35 days |
B. | 15 days |
C. | 30 days |
D. | 25 days |
Answer» B. 15 days | |