If A, B and C together do a job in 4 days, A and C together do the job in 4.5 days and B and C together do the job in 12 days, then in how many days can C alone do the job? |
A. | 36 |
B. | 6 |
C. | 18 |
D. | 12 |
Answer» D. 12 | |