1. |
If A and B together can complete a work in 18 days, A and C together in 12 days and B and C together in 9 days, then B alone can do the work in |
A. | 18 days |
B. | 24 days |
C. | 30 days |
D. | 40 days |
Answer» C. 30 days | |