1. |
If 9 men working$${\text{7}}\frac{1}{2}$$ hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work ? (It is being given that 2 men of latter type work as much as 3 men of the former type.) |
A. | ${\text{9}}\frac{1}{2}$$ |
B. | 1 |
C. | ${\text{12}}\frac{1}{2}$$ |
D. | 3 |
Answer» D. 3 | |