MCQOPTIONS
Saved Bookmarks
1. |
If 5 men or 8 women can do a piece of work in 12 days, how many days will be taken by 2 men and 4 women to do the same work? |
A. | 15 days |
B. | <table><tr><td rowspan="2">13</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">2</td></table> |
C. | <table><tr><td rowspan="2">13</td><td style="border-bottom:1px solid #000000;vertical-align:bottom;padding-bottom:2px;"><center>1</center></td><td rowspan="2">days</td></tr><td align="center">3</td></table> |
D. | 10 days |
Answer» D. 10 days | |