1. |
If 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, the number of days required to complete the work by 5 men and 6 women is |
A. | 7.5 days |
B. | 8 days |
C. | 9.5 days |
D. | 12 days |
Answer» B. 8 days | |