1. |
If 45 persons can complete a work in 18 days, working 8 hours a day, then how many persons are required to complete two-thirds of the same work in 20 days, working 9 hours a day? |
A. | 24 |
B. | 40 |
C. | 36 |
D. | 30 |
Answer» B. 40 | |