1.

If 34 men completed 2/5th of a work in 8 days working 9 hours a day. How many more man should be engaged to finish the rest of the work in 6 days working 9 hours a day ?

A. 101 men
B. 112 men
C. 102 men
D. 120 men
Answer» D. 120 men