If 24 men can do a piece of work in 27 days working 7 hours per day, in how many days can 14 men do it working at the rate of 9 hours per day? |
| A. | 28 |
| B. | 30 |
| C. | 36 |
| D. | 35 |
| Answer» D. 35 | |