1.

If 200 men can dig a canal working for 8 hours a day in 6 days, how long will it take to dig the canal, if 300 men work 6 hours per day?

A. \(5\frac{1}{3}\;days\)
B. 6 days
C. \(4\frac{2}{3}\;days\)
D. 7 days
Answer» B. 6 days