

MCQOPTIONS
Saved Bookmarks
1. |
How many workers are required for completing the construction work in 10 days? I. 20% of the work can be completed by 8 workers in 8 days. II. 20 workers can complete the work in 16 days. III. One-eighth of the work can be completed by 8 workers in 5 days. |
A. | I only |
B. | II and III only |
C. | III only |
D. | I and III only |
E. | Any one of the three |
Answer» F. | |