MCQOPTIONS
Saved Bookmarks
| 1. |
From the following cost components of a building construction project which is not a direct cost combination ? P. Labour cost Q. Equipment cost R. Material cost S. Establishment cost T. Supervision cost |
| A. | P and Q |
| B. | Q and R |
| C. | P and R |
| D. | S and T |
| Answer» E. | |