| 1. |
For the removal of nitrogen completely through Activated Sludge Process (ASP) what would be the Solid retention time considered? |
| A. | 3-18 days |
| B. | 1-2 days |
| C. | 12 hours |
| D. | 18 hours |
| Answer» C. 12 hours | |