MCQOPTIONS
Saved Bookmarks
| 1. |
For the removal of BOD through Activated Sludge Process (ASP) what would be the Solid retention time considered? |
| A. | 18 hours |
| B. | 1-2 days |
| C. | 10 hrs |
| D. | 3 days |
| Answer» C. 10 hrs | |