MCQOPTIONS
Saved Bookmarks
| 1. |
For an activity, optimistic time duration is 4 days, pessimistic time duration is 11 days and mostlikely time duration is 8 days. The PERT value of time duration is______ days (up to one decimal place). |
| A. | 7.8 to 7.9 |
| B. | 8.8 to 7.9 |
| C. | 7.7 to 8.9 |
| D. | 8.5 to 9.0 |
| Answer» B. 8.8 to 7.9 | |