| 1. |
For a reinforced concrete beam with M 20 concrete with Fe 415 steel, the working moment corresponding to ‘balanced failure’ by the Limit Sate Method of Design is A times of the relatable magnitude of the working moment computed by the Working Stress Method. This value of A is nearly |
| A. | 1 |
| B. | 1.5 |
| C. | 2 |
| D. | 2.5 |
| Answer» D. 2.5 | |