MCQOPTIONS
Saved Bookmarks
1. |
For a reinforced concrete beam with M 20 concrete with Fe 415 steel, the working moment corresponding to ‘balanced failure’ by the Limit Sate Method of Design is A times of the relatable magnitude of the working moment computed by the Working Stress Method. This value of A is nearly |
A. | 1 |
B. | 1.5 |
C. | 2 |
D. | 2.5 |
Answer» D. 2.5 | |