Following data refers to the jobs (P, Q, R, S) which have arrived at a machine for scheduling. The shortest possible average flow time is ____ days. |
| A. | 31 |
| B. | 32 |
| C. | 33 |
| D. | 30 |
| Answer» B. 32 | |