Fee of contractor for a project has the following provisions Basic fee = 15% of actual cost of work incurred Bonus = 20% of savings from estimated cost of work Penalty = 20% of cost overrum If the estimated cost of the project is Rs. 60,000, and the actual cost is Rs. 70,000, then the total fee of contractor in Rupees is ___________ |
| A. | 8500 to 8500 |
| B. | 5500 |
| C. | 3500 to 4500 |
| D. | 6500 |
| Answer» B. 5500 | |