1.

Fee of contractor for a project has the following provisions Basic fee = 15% of actual cost of work incurred Bonus = 20% of savings from estimated cost of work Penalty = 20% of cost overrum If the estimated cost of the project is Rs. 60,000, and the actual cost is Rs. 70,000, then the total fee of contractor in Rupees is ___________

A. 8500 to 8500
B. 5500
C. 3500 to 4500
D. 6500
Answer» B. 5500