1.

Eight persons can finish a work in 20 days. After 5 days they were requested to complete the work in the next 8 days. How many more persons should join the group to fulfil the requirement?_x005F_x000D_

A. 23
B. 15
C. 7
D. 12
Answer» D. 12


Discussion

No Comment Found