Eight persons can finish a work in 20 days. After 5 days they were requested to complete the work in the next 8 days. How many more persons should join the group to fulfill the requirement? |
A. | 12 |
B. | 15 |
C. | 23 |
D. | 7 |
Answer» E. | |