Dash line in the Schedule Test Run ______ . |
| A. | Indicates test to be executed after the previous test, with no condition. |
| B. | Indicates test to be executed only if the previous test has finished. |
| C. | Indicates test to be executed only if the previous test has status passed. |
| D. | It can be blue or green |
| Answer» B. Indicates test to be executed only if the previous test has finished. | |