Consider the following data:1. Work is carried out by a contractor employing labour with 25% overtime per day2. Working for 5 days a week3. Contractor peak manpower is 40 per day4. Build-up period is 20%4. Rundown period is 10%5. Total effort in standard man days is 1200The duration of work by Trapezoidal man power distribution pattern will be |
| A. | 5.5 weeks |
| B. | 6.5 weeks |
| C. | 7.5 weeks |
| D. | 8.5 weeks |
| Answer» B. 6.5 weeks | |