1.

Consider the following data:1. Work is carried out by a contractor employing labour with 25% overtime per day2. Working for 5 days a week3. Contractor peak manpower is 40 per day4. Build-up period is 20%4. Rundown period is 10%5. Total effort in standard man days is 1200The duration of work by Trapezoidal man power distribution pattern will be

A. 5.5 weeks
B. 6.5 weeks
C. 7.5 weeks
D. 8.5 weeks
Answer» B. 6.5 weeks