MCQOPTIONS
Saved Bookmarks
| 1. |
By introducing a dummy activity in a network |
| A. | unique numbering system for different activities is maintained |
| B. | time is consumed additionally |
| C. | logical sequence of activities is disturbed |
| D. | Supply and demand conditions |
| E. | resource is allocated additionally |
| Answer» B. time is consumed additionally | |