1. |
Atul can do piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work? |
A. | 12 |
B. | 6 |
C. | 18 |
D. | 10 |
Answer» C. 18 | |