| 1. |
Atul can do a piece of work in 18 days, Aaravya is 50% more efficient than Atul. How much more time does Atul take than Aaravya to do the same piece of work? |
| A. | 12 |
| B. | 6 |
| C. | 18 |
| D. | 10 |
| Answer» C. 18 | |