1.

At a hydro electric power plant site, available head and flow rate are 24.5 m and 10.1 m3/s respectively. If the turbine to be installed is required to run at 4.0 revolution per second (rps) with an overall efficiency of 90%, the suitable type of turbine for this site is

A. Francis
B. Kaplan
C. Pelton
D. Propeller
Answer» B. Kaplan