At a construction site, 200 workers were working on a building that is scheduled to end within 250 days. After 30 days, 20 workers leave the job. How many days will it take to complete the remaining work?

A. 190 days
B. 186 days
C. 245 days
D. 198 days
Answer» D. 198 days