

MCQOPTIONS
Saved Bookmarks
1. |
Arrange the following activities for making a software product using 4GT. i. Design strategy ii. Transformation into product iii. Implementation iv. Requirement gathering ? |
A. | 1, 4, 3, 2 |
B. | 4, 3, 1, 2 |
C. | 4, 1, 3, 2 |
D. | 1, 3, 4, 2 |
Answer» D. 1, 3, 4, 2 | |