1.

Anil, Dinesh and Deepak together can complete a work in 40 days. Anil and Dinesh together can complete the same work in 50 days. In how many days Deepak alone can complete the same work?

A. 90 days
B. 200 days
C. 150 days
D. 75 days
Answer» C. 150 days