

MCQOPTIONS
Saved Bookmarks
1. |
Anil can do a work in 15 days while Sunil can do it in 25 days. How long will they take if both work together? |
A. | 3 4/9 days |
B. | 8 4/9 days |
C. | 9 3/8 days |
D. | 6 3/8 days |
Answer» D. 6 3/8 days | |