1.

An electrical appliances showroom sells 2,400 ceiling fans in one year (52 weeks). The holding cost is 10% of the cost of the ceiling fan. The cost of one ceiling fan is Rs. 600. The cost incurred for placing an order is Rs. 201. There is a lead time of 5 weeks. The economic order quantity (EOQ) and the reorder level, respectively. (rounded to the next higher integer) are

A. 231, 127
B. 38, 231
C. 127, 231
D. 127, 13
Answer» D. 127, 13