

MCQOPTIONS
Saved Bookmarks
1. |
Amit and Sumit can finish a task in 18 days. Sumit and Shilpi can finish the same task in 12 days. Amit, Sumit and Shilpi together can finish it in 6 days. Amit and Shilpi together can finish it in: |
A. | \(6\frac{1}{7}\) days |
B. | \(4\frac{1}{7}\) days |
C. | \(7\frac{1}{7}\) days |
D. | \(5\frac{1}{7}\) days |
Answer» E. | |