Ajay can do a piece of work in 10 days and Harshal can do same work in 12 days. They started working together but Ajay left the work 2 days before completion of work, then time taken to complete the work? |
A. | \(6 \frac{6}{11}days\) |
B. | \(5 \frac{3}{10}days\) |
C. | \(4 \frac{3}{2}days\) |
D. | \(7 \frac{2}{5}days\) |
Answer» B. \(5 \frac{3}{10}days\) | |