1.

Ajay can do a painting in 12 days. Amit is 70% more efficient than Ajay. What is the number of days Amit would need to finish the same painting?

A. \(6\frac{4}{{15}}\)
B. \(5\frac{1}{{13}}\)
C. \(3\frac{3}{{5}}\)
D. \(7\frac{1}{{17}}\)
Answer» E.