MCQOPTIONS
Saved Bookmarks
1. |
Activity slack or float of any event on a PERT/CPM chart is represented by |
A. | Latest start time of succeeding event earliest finish time of preceding event activity time |
B. | Latest start time of the event earliest start time of the event |
C. | Latest finish time of event earliest finish time of the event |
D. | Anyone of the above |
Answer» E. | |