| 1. |
A works twice as fast as B. If B can complete a work in 12 days independently, the number of days in which A and B can together finish the work in : |
| A. | 4 days |
| B. | 6 days |
| C. | 8 days |
| D. | 18 days |
| Answer» B. 6 days | |