A work when done by 10 women is completed in 12 days. The same work can be completed in 8 days by 5 men. How many days will it take to complete when 6 women and 3 men are employed to perform the same job? |
A. | 12 |
B. | 10 |
C. | 8 |
D. | 5 |
Answer» D. 5 | |