A work could be completed in 100 days. However, due to the absence of 10 workers, it was completed in 110 days then, the original number of workers was |
A. | 110 workers |
B. | 120 workers |
C. | 130 workers |
D. | 140 workers |
Answer» B. 120 workers | |