A welding operation is time-studied during which an operator was pace-rated as 120%. The operator took, on an average, 8 minutes for producing the weld-joint. If a total of 10% allowances are at lowed for this operation. The expected standard production rate of the weldjoint (in units per 8 hour day) is |
| A. | 45 |
| B. | 50 |
| C. | 55 |
| D. | 60 |
| Answer» B. 50 | |