| 1. |
A time study of a machine operation recorded a cycle time of 7, 6, 7, 8 minute. The analyst rated the observed worker 80%. The allowance fraction is 0.1. The standard time is |
| A. | 5.22 minutes |
| B. | 6.22 minutes |
| C. | 7.22 minutes |
| D. | 7.0 minutes |
| Answer» C. 7.22 minutes | |