1.

A time study of a machine operation recorded a cycle time of 7, 6, 7, 8 minute. The analyst rated the observed worker 80%. The allowance fraction is 0.1. The standard time is

A. 5.22 minutes
B. 6.22 minutes
C. 7.22 minutes
D. 7.0 minutes
Answer» C. 7.22 minutes