A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job ? |
| A. | days |
| B. | days |
| C. | 0 days |
| D. | 2 days |
| Answer» D. 2 days | |