A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job ?

A. days
B. days
C. 0 days
D. 2 days
Answer» D. 2 days