MCQOPTIONS
Saved Bookmarks
1. |
A team of 30 men is supposed to do a job in 36 days. After 30 days some more men are employed and work was finished 2 days earlier. Then how many more men were employed? |
A. | 17 |
B. | 15 |
C. | 13 |
D. | 19 |
Answer» C. 13 | |