A takes three times as long as B and C together to do a job. B takes four times as long as A and C together to do the same work, If all three, working together can complete the job in 24 days, then th |
A. | 100 |
B. | 96 |
C. | 95 |
D. | 90 |
Answer» C. 95 | |